| BRIEF LIST OF MAJOR WORKS COMPLETED DURING THE PAST SEVEN YEARS | ||||
|---|---|---|---|---|
| Sl.No. | Customers / Consultants Name | Name of Projects & Details | Period of Completion | |
| 1 | M/s BPCL ,Chepapd | Operation & maintenance of fuel handling facilities at Cheppad and Kayamkulam -2020 | 30 Months | |
| 2 | M/s Petronet LNG Limited , Kochi | ARC for Mechanical & Electrical maintenance work -2019 | 12 Months | |
| 3 | M/s Petronet LNG Limited, Kochi | Design, supply & erection of fire water risers for T-101 & T102 -2020 | 3 Months | |
| 4 | M/s NTPC Limited, Kayamkulam | Rate contract for mechanical maintenance works, NTPC ,Kayamkulam -2017 | 24 Months | |
| 5 | M/s SIMPLEX CONCRETE PILES (INDIA) Ltd, KUDANKULAM,Tamil Nadu. | Fabrication & erection of Structural steel Items of 500 M. T. | 6 Months | |
| 6 | M/s FACTEngineering Works, Udyogamandal , Kochi | Site Erection, Welding & Insulation of CHE & HHE at M/s TTPL,Trivandrum | 1 Month | |
| 7 | M/s KMM Ltd. Chavara, Kerala | Fabricated, supplied & installed two numbers of settling tanks | 2 Months | |
| 8 | M/s Petronet LNG Limited , Kochi | Dismantling, packing & Loading of submerged combustion vaporizer including radiography | 1.5 Months | |
| 10 | M/s Unitech Machines Ltd, Chennai | Pipeline works of IBR and Non IBR with Pipe Rack for Co-Generation Plant at M/s Sakthi sugars Ltd, Sivagangai, Tamil Nadu. | 6 Months | |
| 11 | M/s KMM Ltd. Chavara, Kerala | Fabrication, Erection & commissioning of complete piping of C.S & S.S at Titanuim sponge Project. | 12 Months. | |
| 12 | M/s BPCL ,Chepapd | Maintenance and Servicing of PM works , house -keeping works of office & plant areas, replacement of pipe lines and structural plant and painting of the corroded pipes, structural, tanks, etc | 30 Months | |
| 13 | M/s KMM Ltd. Chavara, Kerala | Structural Replacement work for AMC of 2 years. | 24 Months | |
| 14 | M/s KMM Ltd. Chavara, Kerala | Fabrication, Erection & commissioning of complete piping of C.S & S.S at Titanuim sponge Project. | 12 Months. | |
| 15 | M/sTravancore Titanium Products, Trivandrum | Supply, Fabrication, Erection, and Testing of the Pipe lines works for our Copperas Recovery Plant | 8 Months | |
| 16 | M/s KMM Ltd. Chavara, Kerala | Fabrication, Erection, Testing, Painting of Carbon Steel and SS 304Pipelines including structural supports for the 500TPY Titanium Sponge plant | 6 Months | |
| 17 | M/s Petronet LNG Limited, Kochi | Design, supply & erection of fire water risers for T-101 & T102 -2020 | 3 Months | |
| 18 | M/s KMM Ltd. Chavara, Kerala | Structural Works | 24 Months | |
| 19 | M/s Petronet LNG Limited, Kochi | Mechanical and Electrical maintanance of ARC | 12 months | |
| 20 | Raj & K Engineers India PVT.Ltd, Chennai | Fabrication, Assembly, Erection and Commissioning of Equipments, Tanks, Vessels ans Structurals | 8 Months | |
| 21 | M/s KIDDE INDIA Ltd | Fire Protection system of T.C.S at Navalloo site, Chennai. | 12 Months | |
| 22 | M/s Unitech Machines Ltd, Chennai | Piping work of C.S, S.S & INCONEL including IBR Piping for Zircunion Complex, of M/s Nuclear Fuel Complex at Palayakayal, Tuticorn, Tamil Nadu | 8 Months | |
| 23 | HINDUSTAN NEWSPRINT Ltd, Kottayam, Kerala. | Replacement of Inbed Tubes of 3 Nos Power Boiler- IBR | 45 days | |
| 24 | NTPC Ltd. RGCCP,kayamkulam. | AMC for Plant Mechanical Maintenance. | 3 Months. | |
| 25 | M/s AGNICE FIRE PROTECTION Ltd, CHENNAI. | Fire Protection & Detection systems at KMML Chavara for TSP Project. | 12 Months | |
| 26 | NTPC Ltd. RGCCP,kayamkulam | Overhauling of Boilers & Replacement of IBR Pipelines | 30 days | |
| 27 | M/s ECOMAN, Vadodara, Gujarath | Assembly & Erection of equipments, Tanks & Vessels at KMML Chavara for TSP Project. | 30 days | |